US hyperscale data centres used 82 TWh of electricity in a year

The Verge reports about 54% of their electricity is likely from gas and coal; researchers had to estimate the totals.

By the numbers

Figures from this story's sources.

Metric tons of CO2 emitted by the 403 facilities, per The Verge Source for 25.7 million (opens in a new tab)
25.7 million
Electricity used by the 403 US hyperscale facilities in one year Source for 82 TWh (opens in a new tab)
82 TWh
Share of all US electricity consumption, per The Verge Source for 1.8% (opens in a new tab)
1.8%
Share of facilities' electricity likely from gas and coal Source for 54% (opens in a new tab)
54%

Gianluca Guidi, a postdoctoral fellow in biostatistics at Harvard's public health school, is the lead author of a study that puts US hyperscale data centres at about 82 terawatt-hours of electricity in a single year. The Verge reports that the study was published in the journal Nature Sustainability. Using satellite imagery, the researchers identified 403 facilities, which together used about 1.8% of all US electricity consumption, according to The Verge. John Sterman, director of the MIT System Dynamics group, says 82 TWh is more than about 148 nations use in a year.

Emissions are the sharper number. Fast Company reports that the facilities emitted more than 25 million metric tons of CO2 between 2024 and 2025, about three times the 2018 level for US hyperscale data centres. The Verge gives a figure of 25.7 million metric tons and says it is comparable to Denmark's annual carbon footprint. Sterman, as The Verge reports, says the figure is higher than the total emissions of about 113 nations. The outlets describe the period differently: Fast Company says 2024 to 2025, while The Verge says May 2024 to April 2025.

Grid mix matters, according to The Verge. It reports that about 54% of the facilities' electricity is likely from gas and coal. It also says Wyoming's coal-reliant grid emits roughly seven times more CO2 per kilowatt-hour than Oregon's hydropower-rich grid.

Operators do not disclose energy data, so researchers had to estimate consumption, The Verge reports. They estimated each site's power use from its electrical capacity. For emissions, they used EPA data from May 2024 to April 2025 to estimate what each facility would emit if connected to its local grid. The study does not account for local air pollution from new gas infrastructure built for data-centre demand, or from on-site gas turbines some AI companies use. Hyperscale facilities are a fraction of the thousands of US data centres, and more are added each year, per The Verge.

Why it matters

Operators do not publish their energy use, so any estimate of their carbon exposure rests on modelled figures, and the grid they draw from moves the carbon total. Sterman, as The Verge reports, says policymakers should require operators to bring new clean energy online. For AI companies running on-site gas turbines, the study does not account for local air pollution from those turbines, so that exposure is not measured here. Fengqi You, a Cornell energy systems professor who was not involved in the study, warns of "long-term carbon lock-in", and The Verge paraphrases him as saying plants built for data-centre demand may run for decades.

Sources

Checked against 2 outlets

  • Fast Company — Emissions of more than 25 million metric tons of CO2 for 2024 to 2025, about three times the 2018 level, and the 2024 to 2025 time framing.
  • The Verge — Study publication in Nature Sustainability, lead author, method, 403 facilities, 82 TWh, 1.8% share, 25.7 million metric tons, grid mix, exclusions, and expert comments from Sterman and Fengqi You.

Found something wrong? Our corrections policy explains how to tell us. How we report the news. Add Outgrace as a preferred source on Google.